Work on schedule for high school concert hall

Team Radio Marketing Group - September 22, 2017 3:04 pm

A building progress report prepared by Lewis Associates Architects earlier this month shows construction of the Ponca City High School Concert Hall is on schedule to meet the substantial completion goal of Aug. 3, 2018.

The guaranteed maximum price (GMP) for the project is $9,729,361.21. Approved payments by Sept. 5 totaled $1,041,070.11.

The project started in March 2017.

In early September, the report said about 85 percent of the floor slab installation was complete. The most striking change in the landscape is the elevator tower which rises to the north of the auditorium floor.

 

 

Latest Stories

Update: 5 PEOPLE FOUND DEAD, INCLUDING 2 CHILDREN, IN SW OKLAHOMA CITY HOME

YUKON, Okla. – Oklahoma City police discover five people dead including two children, inside a home...

HOUSEHOLD HAZARDOUS WASTE COLLECTION DAY IS APRIL 27, 2024

Are you wondering how to safely dispose of the poisons, antifreeze or chemicals you cleaned out...

PO-HI Orchestra Takes Home Several Awards

Members of the Po-HI Orchestra traveled to OSU this past Tuesday for the OSSAA Solo and...