Work on schedule for high school concert hall

Team Radio Marketing Group - September 22, 2017 3:04 pm

A building progress report prepared by Lewis Associates Architects earlier this month shows construction of the Ponca City High School Concert Hall is on schedule to meet the substantial completion goal of Aug. 3, 2018.

The guaranteed maximum price (GMP) for the project is $9,729,361.21. Approved payments by Sept. 5 totaled $1,041,070.11.

The project started in March 2017.

In early September, the report said about 85 percent of the floor slab installation was complete. The most striking change in the landscape is the elevator tower which rises to the north of the auditorium floor.

 

 

Latest Stories

Oklahoma COVID-19 Update for 18 June 2021

Situation Update: COVID-19 COVID-19 Cases 455,535 New Cases 181 New Cases 7 day Average 163 Active...

Ziegler Estate Funds Transformational Gift to OU Foundation

Provides Support of Nursing, Cancer Research, Scholarships, Sam Noble Museum and More The gift provides over $45...

Historic building in downtown Eufaula collapses

EUFAULA, Okla. (KFOR) – In the summer, many Oklahoma families enjoy heading to local lakes across...