Work on schedule for high school concert hall

Team Radio Marketing Group - September 22, 2017 3:04 pm

A building progress report prepared by Lewis Associates Architects earlier this month shows construction of the Ponca City High School Concert Hall is on schedule to meet the substantial completion goal of Aug. 3, 2018.

The guaranteed maximum price (GMP) for the project is $9,729,361.21. Approved payments by Sept. 5 totaled $1,041,070.11.

The project started in March 2017.

In early September, the report said about 85 percent of the floor slab installation was complete. The most striking change in the landscape is the elevator tower which rises to the north of the auditorium floor.

 

 

Latest Stories

Top-seeded Thunder on the verge of series loss to Mavs

By SCHUYLER DIXON AP Sports Writer DALLAS (AP) — A kinder, gentler Luka Doncic has the...

House Sends Disaster Relief Bills to Senate

OKLAHOMA CITY – Following numerous tornadoes across the state this spring, the Oklahoma House of Representatives...

Area Forecast

Today Areas of fog before 10am. Otherwise, mostly cloudy through mid morning, then gradual clearing, with...