US-177 pavement resurfacing project starts in Blackwell Monday

Mike Seals - June 11, 2021 9:33 am

A pavement resurfacing project on northbound and southbound US-177/S. Main St. between Chrysler Ave. and SH-11 in Blackwell is expected to begin at 8 a.m. Monday, June 14. Motorists can expect intermittent lane closures daily one mile at a time within the 3-mile project length through fall 2021. Drivers should plan extra travel time through this area and expect delays.

The $2.5 million contract was awarded in February 2021 to Evans & Associates Construction Co. Inc. of Ponca City. The project is expected to complete by fall 2021, weather permitting.

 

Latest Stories

Tulsa Community College selected for the Metallica Scholars Initiative

TULSA, Okla. — Tulsa Community College has joined the sixth cohort of the Metallica Scholars Initiative. The...

Oklahoma ranks second worst in education, amidst new curriculum controversy

Tulsa, Okla. (KTUL) — State Superintendent Ryan Walters has issued guidance on the requirement for Oklahoma school...

Southwest Airlines Announces Changes To Seating Policy, Adds Overnight Flights

DALLAS – Southwest Airlines announced on Thursday the company will soon do away with the existing first-come-first-serve...