Roof Projects at East and West Middle Schools

Mike Seals - June 24, 2021 9:39 am

 

Construction projects this summer for Ponca City Public Schools includes two roofing projects at East and West Middle Schools.

Bret Smith, Executive Director of Operations for PCPS, said these two projects were previously approved by the insurance company to be redone but never got on the schedule. “We had money left from the additional emergency reroof project that we did at all three secondary schools so we put both projects out to bid,” said Smith. “The money is still there for us to use.”

Smith said the wrestling room addition at East Middle School, which was built back in 1974, was beginning to leak. “They are finishing up some work now but it’s about 98 percent finished.”

“West Middle School was the same scenario,” said Smith. “The lower roof over the band room and a couple of classrooms and a hallway on the east side of West needed repairs. That project is starting either this week or next as they are trying to finish up at East.”

American Roofing in Ponca City was the low bidder on both projects. The cost for East Middle School was $123,547.55 while the cost at West Middle School was $226,528.20.

The project, according to Smith, should be finished by the time school starts in August.

BELOW:  Roof equipment is lifted at West Middle School to allow for the roofing project this summer. The roof on the east side of the school that includes the band room, a couple of classrooms and a hallway will be repaired.

 

Latest Stories

Ancient tablet acquired by Hobby Lobby going back to Iraq

WASHINGTON (AP) — It was looted from an Iraqi museum 30 years ago. Now, a 3,500-year-old...

Oklahoma higher education regents announce new chancellor

OKLAHOMA CITY (AP) — The Oklahoma State Regents for Higher Education have announced that the president...

Stitt calls special session for redistricting

OKLAHOMA CITY (AP) — Oklahoma Gov. Kevin Stitt has called a special session of the Legislature...