Judge keeps most Keystone XL pipeline work on hold

The Associated Press - February 16, 2019 11:00 am

BILLINGS, Mont. (AP) – A federal judge in Montana has largely kept in place an injunction that blocks a Canadian company from performing preliminary work on the stalled Keystone XL oil pipeline.
U.S. District Judge Brian Morris on Friday denied a request by Calgary-based TransCanada to begin constructing worker camps for the 1,184-mile pipeline that would ship crude from Alberta, Canada to the Gulf Coast.
However, Morris said TransCanada could perform some limited activities outside the pipeline’s right-of-way. Those include the construction and use of pipe storage and container yards.
TransCanada attorneys had argued the injunction issued by Morris in November could cause it to miss the 2019 construction season and further delay the project.
An appeal of November’s ruling is pending before the 9th U.S. Circuit Court of Appeals.

 

Latest Stories

2 killed in second fire at Tulsa church damaged by July blaze

TULSA, Okla. (AP) — Authorities continue investigating the cause of a deadly fire in which two...

Tulsa doctor, workers charged in patient deaths

TULSA, Okla. (AP) — A Tulsa doctor and two of his former employees are facing federal...

Oklahoma treasurer reports slump in November collections

OKLAHOMA CITY (AP) — Oklahoma Treasurer Randy McDaniel says that overall collections to the state treasury...