Work on schedule for high school concert hall

Team Radio Marketing Group - September 22, 2017 3:04 pm

A building progress report prepared by Lewis Associates Architects earlier this month shows construction of the Ponca City High School Concert Hall is on schedule to meet the substantial completion goal of Aug. 3, 2018.

The guaranteed maximum price (GMP) for the project is $9,729,361.21. Approved payments by Sept. 5 totaled $1,041,070.11.

The project started in March 2017.

In early September, the report said about 85 percent of the floor slab installation was complete. The most striking change in the landscape is the elevator tower which rises to the north of the auditorium floor.

 

 

Latest Stories

Edwards Scores 43 Points, Reid Erupts in 4th to Help Timberwolves Beat Nuggets 106-99 in Game 1

DENVER (AP) — Anthony Edwards’ decision-making was as spot-on as his shot-making. When he drew a...

Mystik Dan Wins 150th Kentucky Derby by a Nose in the Closest 3-Horse Photo Finish Since 1947

LOUISVILLE, Ky. (AP) — The 150th Kentucky Derby produced one of the most dramatic finishes in its...

Chet Holmgren and Lu Dort anchor elite Thunder defense heading into second round of NBA playoffs

By CLIFF BRUNT AP Sports Writer OKLAHOMA CITY (AP) — The young Oklahoma City Thunder finally...